Well in my case (so far) 4 months and counting. Last update from OR...
A new A55 (engineer's diagram) is required in order to complete the incremental build task. The previous build task could not be completed by the contractors due insufficient information in the original A55. A new estimate is now required and this order has been referred to our planning team for review.
We have been advised that our planning team are still reviewing this matter therefore we will need to allow some additional time for further updates to be provided.
Next review will be set for (03/11/26)."
that followed
"This order is awaiting completion of Incremental Build estimate (WH4CV22D) which is currently in progress. We previously escalated this with the relevant team who advised an engineer would be attending on (24/09/26) to investigate the delay and provide a new A55 (engineer's diagram).
I am unable to see if an engineer visit took place on the given date therefore I have escalated this with the relevant team today for an urgent update.
Next review will be set for (06/10/26)."
And that was after
What has happened- A civils estimate, WH6JM70N, has been raised with an expected start date of 08/10/2026. The civils team is currently awaiting the necessary permissions and approvals from the utility companies in the area before the work can proceed.
What have you done- I have checked the latest update and can see that the job is currently in the noticing stage. The case is awaiting the relevant traffic management permit to be raised and approved before the civils work can be scheduled.
What happens next? ? Once the required traffic management permit has been approved, the civils team will be able to progress the estimate and schedule the work. If there are no further updates, I will raise an escalation with our partner contractor to request an update on the permit status and the planned works.
When will the cp/cx hear from you again? ? I will review the order on 07/09/2026 and to check engineer’s task is active
Sigh... The job started on 10th June this year(!) and yes, it isn't enirely straight forward so some delay is expected. There is an existing leased line fibre duct to the premises (to the same location as the new install) so that should help (or would it?) - it might have two fibres in it but possibly just 1 (depends if they changed the fibre when they upgraded it from 100Mbps to 1Gbps the other year and no, I can't just piggyback on that for voice becasue reasons; there is ample bandwidth but its not 'my' fibre)
The end of January is rapidly approaching (at least in OR planning terms) so I do hope they extract a digit from whatever warm place it is currently resting and get on with the job!
I guess it will happen eventually