I my exchange has been enabled for a while but I have been unable to get Fibre as my cabinet (and various others around my area of town) was bypassed.

I randomly checked the Postcode checker today and saw that it now says the following:

£Your cabinet is planned to have WBC FTTC by 31st December 2012. Our test also indicates that your line currently supports a fibre technology with an estimated WBC FTTC Broadband where consumers have received downstream line speed between 45.5 to 57.6 Mbps and upstream line speed between 8 to 20 Mbps."

I am aware that some people on this forum have access to slightly more data than is available on the post code checker. Could somebody please let me know if the above date looks like it will be accurate?

My post code is KY118GJ

Many thanks
Standard User RobertoS
(sensei) Sat 10-Nov-12 17:36:01
Print Post

Re: Cabinet help please


[re: Bigmonty] [link to this post]
 
Looks like cabinet 86? Phase 9b so looks about right - but the only public data is dated December 2011.

What you have just posted is the best public guide to the state of things now, as it seems all lines at your postcode are on that cabinet. Don't be surprised if in the last week of December it changes to 31 March 2013.

Postcode checks are the worst option. If the checker won't accept your phone number, always use the full address, in case not all lines are on the same cabinet. (That's advice for anyone else in your position, and even for you as there may be errors in the December 11 data).

My broadband basic info/help site - www.robertos.me.uk | Domains,website and mail hosting - Tsohost.
Connection - Plusnet Extra Fibre (FTTC). Sync ~ 53.5/15.2Mbps @ 600m. - BQM

"Where talent is a dwarf, self-esteem is a giant." - Jean-Antoine Petit-Senn.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Allergy information: This post was manufactured in an environment where nuts are present. It may include traces of understatement, litotes and humour.
Standard User Bigmonty
(newbie) Sun 11-Nov-12 08:35:28
Print Post

Re: Cabinet help please


[re: RobertoS] [link to this post]
 
Thanks Roberto. I actually did put my whole address in like you suggest, I just worded my initial post badly.

To be honest if it slips to March 2013 then so be it. I am just happy that my cabinet is not one of those on an exchange which are "not commercially viable".

Cheers


Register (or login) on our website and you will not see this ad.

Standard User iwish
(committed) Sun 11-Nov-12 14:31:23
Print Post

Re: Cabinet help please


[re: Bigmonty] [link to this post]
 
We have 3 phone cabinets in our village, all three had big holes next to them and 2 where filled with fibre cabs and one just got filled back in.
never get yur hopes up until you see the big green cab go in
Standard User Ribble
(committed) Sun 11-Nov-12 20:41:18
Print Post

Re: Cabinet help please


[re: iwish] [link to this post]
 
never get yur hopes up until you see the big green cab go in

And very rarely a cabinet is fitted but never goes into service, eventually getting removed.
Standard User Bigmonty
(newbie) Sun 11-Nov-12 23:09:21
Print Post

Re: Cabinet help please


[re: Ribble] [link to this post]
 
Thanks for the replies. My word it's all doom and gloom on this site wink

I have another question. I noticed on the roadworksscotland website that there are works scheduled by BT at 2 cabinets next to mine for this month. If it turns out that they are upgrading those cabinets what's the likelyhood that they'll finish the other ones in phase 9b or do BT just dart around the country randomly?
Standard User ccxo
(experienced) Mon 12-Nov-12 00:06:44
Print Post

Re: Cabinet help please


[re: Bigmonty] [link to this post]
 
Most cabinets have their FTTC twin enabled in the phases but delays caused by duct blockages and power issues etc do cause cabinets to slip by a few months or longer while the issues are sorted out.

My Broadband Speed Test
Standard User Bigmonty
(newbie) Tue 13-Nov-12 13:49:15
Print Post

Re: Cabinet help please


[re: ccxo] [link to this post]
 
Thought I'd share a reply I received today to an e-mail I sent to Openreach:

"Thank you for your email

Information about the commercial fibre project can be found on the rollout site :-
http://www.superfast-openreach.co.uk/where-and-when/

In your locality work is ongoing. Currently this is awaiting power and other works. The estimated date for Dunfermline cabinet 86 enablement is close March 2013 assuming there are no major issues.

Your Communications Provider (CP) is responsible for all aspects of your service including advising on the services they can supply at your address. Please contact your CP to register your interest so they are aware and can contact you at such time in the future as they have additional information."


So I guess what people were saying about the Dec 12 date getting put back is correct but hopefully it looks positive for getting FTTC within the next 6 months.
Standard User Bob_s2
(committed) Tue 13-Nov-12 14:33:51
Print Post

Re: Cabinet help please


[re: Ribble] [link to this post]
 
Quite why that haapens is difficult toimage. If they get as far as putting a cabinet in a lot of the costs would have been incurred. Even stranger is the practice BT have of installing the cabinett and then leaving it for several months as BT will have picked up most of tthe costs but will be getting no renues from it.
Administrator MrSaffron
(staff) Tue 13-Nov-12 14:45:08
Print Post

Re: Cabinet help please


[re: Bob_s2] [link to this post]
 
Depends on whether its just the shell or it holds all the electronics and mains connected and fibre ducting in place and ducting to PSTN cab is present.

In short it depends on many variables - am sure that your csv takes these into account though

Andrew Ferguson, [email protected]
www.thinkbroadband.com - formerly known as ADSLguide.org.uk
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
Standard User Bob_s2
(committed) Tue 13-Nov-12 15:29:12
Print Post

Re: Cabinet help please


[re: MrSaffron] [link to this post]
 
The cabinets normally come complete as they are staged in the factory before shipping to site. So you are looking at several thousand pounds worth of kit plus some labour and transport cost sitting idle for several months. Clearly you are not going to get it down to one day but these cabinet installs could be don a lot more efficiently and cost effectively.
The biggest variable is probably getting the fibre to the cabinet so it would be logical to do that first before thinking about placing the cabinet
Administrator MrSaffron
(staff) Tue 13-Nov-12 15:37:50
Print Post

Re: Cabinet help please


[re: Bob_s2] [link to this post]
 
So before thinking about placing the cabinet or you feed the fibre? To where, you've not yet thought about where the cabinet would go, what size, is power available etc

Andrew Ferguson, [email protected]
www.thinkbroadband.com - formerly known as ADSLguide.org.uk
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
Standard User Bob_s2
(committed) Tue 13-Nov-12 15:47:26
Print Post

Re: Cabinet help please


[re: MrSaffron] [link to this post]
 
THe suvry would be done before anything so you would know where the cabinet was going and you would no where the nearest power is. There are very few locations where power is more than a few metres away as the cable runs down the road
Standard User WWWombat
(experienced) Tue 13-Nov-12 16:17:47
Print Post

Re: Cabinet help please


[re: Bob_s2] [link to this post]
 
I think you're right that the cabinet is pre-built in a warehouse, and arrives on-site in a pretty-much working state.

However, I guess the "lost" money isn't in the value of the cabinet (or the included kit) - as that can be re-deployed elsewhere.

We've also seen that some cabinets can end up left unused for quite a while, so BT obviously aren't overly worried about the lost income from a small number of cabinets - especially if the big picture has sufficient custom coming in.

That leaves us with the fact that the real lost money is in the civil engineering work to prepare the site - build a concrete plinth, and set the ducting within it.

While pulling fibre is probably the variable with the biggest distance involved, it is also within BT's control more readily. And where the fibre is part of a spine, then there is more than 1 cabinet to bring into the equation.

However, I don't think the fibre itself amounts to the biggest variable - even if there are duct blockages - in terms of cost.

I think the biggest variable comes down to power again - but this time *not* in the distance that the power has to be connected, nor in the leadtime that an order has to be placed.

Instead, I think that the cases where an installed cabinet suddenly becomes so unviable it is worth removing (and yet was once viable in the spreadsheets) come down to a huge price spike in supplying power. It might be because power isn't available where the planners thought it was, but I bet the real reason is when transformers or substations need a (pretty costly) upgrade, and the charge is planted 100% at BT. In such circumstances they might as well wait until someone else foots the bill. A property developer perhaps, or the council.
Administrator MrSaffron
(staff) Tue 13-Nov-12 16:19:12
Print Post

Re: Cabinet help please


[re: WWWombat] [link to this post]
 
Can't be power as Bob told us that is only an issue very rarely.

Or is Bod wrong?

Andrew Ferguson, [email protected]
www.thinkbroadband.com - formerly known as ADSLguide.org.uk
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
Standard User WWWombat
(experienced) Tue 13-Nov-12 17:08:14
Print Post

Re: Cabinet help please


[re: MrSaffron] [link to this post]
 
I think it is safe to say that the cases where a cabinet goes in, to later be labelled as unviable, are distinctly rare events!
Standard User R0NSKI
(experienced) Wed 14-Nov-12 10:25:49
Print Post

Re: Cabinet help please


[re: WWWombat] [link to this post]
 
Or they put it in the wrong place, like one of ours which appeared on street corner, it has now been removed, and has not been relocated. I wonder if they will put a cabinet back for the pcp involved.

Standard User WWWombat
(experienced) Wed 14-Nov-12 13:01:09
Print Post

Re: Cabinet help please


[re: R0NSKI] [link to this post]
 
That's another one. I guess the financial viability isn't going to change much, but it will very much depend on whether there is an alternative location within 50-100 metres.
Standard User garethr
(newbie) Wed 14-Nov-12 18:33:26
Print Post

Re: Cabinet help please


[re: Bigmonty] [link to this post]
 
If it helps I've seen this where a long run for power is required across a major road.

Another gotcha is where they need traffic lights for health and safety reasons. That seems to take a bit of time to organise.

I suspect you'll see that sorted before March.

All the best

Regards,

Gareth

In reply to a post by Bigmonty:
Thought I'd share a reply I received today to an e-mail I sent to Openreach:

"Thank you for your email

Information about the commercial fibre project can be found on the rollout site :-
http://www.superfast-openreach.co.uk/where-and-when/

In your locality work is ongoing. Currently this is awaiting power and other works. The estimated date for Dunfermline cabinet 86 enablement is close March 2013 assuming there are no major issues.

Your Communications Provider (CP) is responsible for all aspects of your service including advising on the services they can supply at your address. Please contact your CP to register your interest so they are aware and can contact you at such time in the future as they have additional information."


So I guess what people were saying about the Dec 12 date getting put back is correct but hopefully it looks positive for getting FTTC within the next 6 months.