Anyone know how long it normally takes for a cabinet to go live after installation?
Where I am is scheduled to get FTTC by 31st March but no sign of a cabinet yet. From previous experience it can be over 6 months from the cabinet being installed to accepting orders. So is that March date completely unrealistic?
Sometimes a week, sometimes months, sometimes it's there for months and Openreach come back and remove it.
I've had an FTTP fibre aggregator sat in the manhole at my doorstep for 18+ months now and still can't order fibre...
Just a matter of waiting an indeterminate amount of time I'm afraid.