Seems to be some activity at last...
BT have planned roadworks for 16th - 29th July in two lots.
1) High impact, delays likely
Location : s/o 28 High St on BRIGHTON ROAD...
Description : Install 2m of 1 way poly duct in Footway...
That's right by Cab 5 (see link)
2) High impact, delays likely (you can say that again)
Location : o/s 28 across c/w to O/S 59 HIGH STREET...
Description : Install 10m of 1 way poly duct in Carriageway,Install 5m of 1 way poly duct in Footway...
Which appears to be then putting ducting towards Cab 5's fibre twin and that has had power on for some weeks....
This view shows Cab 5 on the right against the wall at No 28 and then opposite side of carriageway at the left is No 59 with the fibre twin now erected a little way off down the left
HERE against the wall by the Roundabout sign (also the public toilets, I hope it's waterproof as there's a pub nearby).
If anyone knows or can guess more...
The last info I had from Openreach guys was they couldn't get the fibre feed on down the High Street (straight ahead in first view) due to ducting problems. nga enquiries estimated 1st August a few weeks back for Cab 4 but that sounds unlikely now I guess...
Edited by tbailey2 (Thu 20-Jun-13 14:33:48)