Worked finished on upgrading the cabinet I'm connected to about 4 weeks ago. I'm still not able to order an FTTC connection.
How long did it take for you guys to be able to order FTTC once the cabinet was up?
|
|
|
|
3 months.
|
|
|
Can be weeks/months. can try emailing [email protected] and they may give you an update or post exchange/cab number and someone maybe able to find out
|
|
Register (or login) on our website and you will not see this ad.
|
|
|
Perhaps it would be a good idea if this thread was stickied, this seems to come up on a weekly basis now.
There is no set time, it could be a matter of weeks, months or even over a year. We have one cab in our area installed last May, and still not live.
It all depends on whether fibre is already installed, and whether there are any problems connecting power, tie cable's and fibre, they are all normally done at different times.
|
|
|
|
Thanks for the info guys and I'm surprised how fast you guys answered.
I have sent openreach an email as suggested. Up to 15 working days for a reply ... that's 3 weeks! If it takes that long to reply to email, I can see why it takes so long to get a FTTC working.
|
|
|
|
It used to be about 2 weeks, they have alot of requests and its a small team so better to say 3 week wait and reply to you before then.
FTTC rollout in any area depends on alot of factors, why some areas will be enabled quicker then others, openreach should give a good rough idea when it will be live.
|
|
|
|
I think part of the problem is all the stories going around about what it involves.
Some say they cabinet is installed and then they connect to power.
While in our case, they dug the trenches for the power and to the BT junction boxes, layed out concrete base for the cabinet, installed the cabinet and connected the power, filled in the holes and then leaving the cabinets.
Think the major work will be blowing the fibre.
Do they blow a fibre from the exchange for each box, or is there like a back bone system with feeder cables from the box to the backbone?
I guess some of us can't understand why when they can install the cabinets that quickly, why they can't actually do the fibre runs that quickly.
Simon
|
|
|
|
Openreach actually replied to me with in a couple of hours, which was surprisingly quick. They said it just needs testing and commissioning before it goes live.
|
|
|
The reality is that it varies. Cabinets are off-loaded with all the kit in them, so that part is pretty quick.
The fibre blowing depends on the state of the ducting and how busy that team is doing all the other jobs.
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
|
They run a spine cable from the exchange to point (node) somewhere outside which contains multiple fibres. Then fibres are blown from the node(s) to the caionets, or often via other node(s) to the cabinets.
The problems with getting the fibres in are usually down to blocked or full duct routes, which then require digging/excavating.
|