Because it's crossing a road so will need traffic control that job needs more notice than building a DSLAM would.
It may also not be related in any way to NGA.
Agreed, we have a similar roadworks job about to start between our exchange and our home which is down as "
Safe Access to Underground BT footway and carriageway boxes for fibre cabling and jointing works in existing duct. Required for new customer connection" its also down with "
Some carriageway incursion" and that was submitted a month before the work was due to start.
Also saw this on the roadworks site:
Build 2 concrete chamber 1310mm x 610mm x 1265mm deep in Footway,
Build 2 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,
Build 3 concrete chamber 915mm x 445mm x 965mm deep in Footway,
Demolish 5 existing jointbox(s) or cabinet base(s),
Erect/Renew 1 PCP cabinet and base (600mm x 300mm x 1000mm),
Install 13m of 2 poly ducts in Footway,
Install 15m of 8 poly ducts in Footway,
Install 22m of 5 poly ducts in Carriageway,
Install 25m of 1 way poly duct in Footway,
Install 4m of 5 poly ducts in Fo
It might of had more but the rest was cut off, but all down as one job, sod doing all that LOL.
Paul