Location:
RESHELL JRF10:80, JCN **** ROAD, ****LANE
Description:
Erect/Renew 1 PCP cabinet and base (600mm x 300mm x 1000mm),Install 2m of 4 poly ducts in Verge
I censored the names of the road/lane for anonymity purposes, but I was wondering what this exactly means? Openreach's website has said my cabinet has been in the "Connecting" stage for the past 6 months or so, and it appears my cabinet keeps getting delayed for FTTC activation.
I contacted my local authority about this a week or two ago and they said my cabinet needed to be "reshelled" and is "on track for delivery by March 2017".
The roadworks specified finishes on 16th February, can I expect to be able to order fibre after this cabinet reshelling is finished or what?