Hi all,
I've recently bought a house where unfortunately the wholesale checker shows 'Waiters list' for FTTC.
Whilst I was waiting for the purchase to go through I was checking every few days and could see it occasionally show 'Available' then 'Waiters list' a couple of days later, however now I've moved in sods law it's been stuck at 'Waiters list' for ages.
I'm not even going to bother ordering ADSL as the village is 7km+ from the exchange so speeds are <500k.
I've been in touch with the Digital Durham programme who, whilst are no longer involved as they only had funding for the original cabinet, have managed to get in touch with Openreach who have said that an additional cabinet is needed and they are waiting for a wayleave signature to commence work.
Does anybody know how long this process of installing a new cabinet takes? Are we talking weeks/months? The original cabinet is one of the small single door cabs and has been full for 3-4 months at least.