For months there was an entryon broadband chacker to say "FTTPOD" was available with 300/30. This morning this has changed to "FTTP on Demand" 1000/200.
My question is, given that it is standard FTTP that is being rolled out, is the change from FTTPOD330/30 to FTTP On Demand 1000/200 just a process that OR go through before offering normal FTTP. if so, how long would it normally take to change from FTTP On Demand to 'normal' FTTP?
This is my current running timeline. Took 3 days for the FTTPoD 1000/200 to change to WBC 1000/200 and become orderable. Your mileage may vary!

I'm still a ways away from having service, but with each step it gets closer.
27/07/2020 - Openreach survey, pavement markings appear in our courtyard off street.
31/07/2020 - Evening works in road, pulling stuff off huge drums through the street ducts.
10/12/2020 - Flower beds in front of neighbour's houses have new chambers installed using existing ducts to street.
20/01/2021 - Fibre CBT installed in flowerbed chamber by Openreach contractors RDJ Utilities.
24/01/2021 - A peek indicates thoughts that I'm on direct buried armoured copper seemingly confirmed.
25/01/2021 - Tails of CBT spliced in a large chamber across the road, in the back of an RDJ Utilities van.
31/01/2021 - Openreach wholesale checker still doesn't offer FTTP, but FTTPoD has been upgraded from 330/30 to 1000/220.
03/02/2021 - Openreach wholesale checker now offers WBC FTTP 1000/220.
04/02/2021 - Ordered 900/115 from Zen over phone. Status on order tracker "Wait for KCI-2". No date for install yet, but claimed single visit(!)
05/02/2021 - Noted OR checker says "Single Dwelling Unit Residential UG Pre built to curtilage Hard." - usually 2 (or more) stage install...
08/02/2021 - OR engineer arrived to survey, looks like plan is to intercept duct either in our flower bed or at edge of drive. Duct proved clear.
09/02/2021 - Email from Zen, 1st stage external install schedule 27/04/2021, 2nd stage internal install appointment 07/05/2021.
14/02/2021 - DIY installed 22mm barrier pipe as conduit from outside wall to inside wall ready for fibre with a couple of draw ropes.
22/02/2021 - Email from Zen, civils work confirmed required and scheduled complete by 03/01/2021. I asked if we could improve on date.