You picked the wrong product if you think this is taking too long.
...
That was 4 months from order to activation,
For what it's worth, the progress of my order so far was as follows:
* Late March - applied for desk quote
* One day later - received desk quote, asked for final quote
* Early July - received final quote, order placed
* Late August - overhead cabling completed, spools of fibre seen hanging from poles along my road
* Late October - 3x blocked ducts cleared via roadworks (rejected twice by the local authority, third time succeeded)
I've not had this week's update, but I reckon it won't be long before I need to book an appointment with an engineer to run cabling into the house.
I'm not worried by the wait (after all, it's worth waiting for) and throughout Cerberus have been helpful, chasing things on my behalf and giving regular updates. As the permits alone will have cost Openreach £2,250, I can't see they'll make much profit from this install - which cost £3,350ish (+VAT).
It's worth noting that a side effect of this is that the whole street will be enabled for standard FTTP once my install goes live - I suspect as part of the "fibre first" initiative.
EDIT: And this week's update from Cerberus advises only one of the three duct clearances was in fact successful - the council didn't reply to the other two requests. That'll be another £500 down the drain for Openreach and possibly another two months' delay (as the work needs to be done outside a school, the council refused the permits before as work can only take place during school holidays, apparently.)
Edited by deleted (Thu 25-Oct-18 16:42:00)