Cab 93 is just off Fleet Road in Cove.
Most of the cabs in that area went live between July and September so they are progressing well, but inevitibly some cabs do get delayed due to reasons usually outside Openreach's control, anything from palnning issues (some council's can take AGES to reply to planning issues or helping to resolve it), awaiting contracters to feed low voltage power to the cab, and of course getting the fibre cabling to the cab. Then there are highway's agency who need to be involved if it involves road works and pavement closures etc.
No doubt it's in Openreach's best interest to have the remaining cabs live ASAP and they are usually doing everything they can to progress things.
The following cabs are still planned but outstanding:
1, 2, 5, 21, 30, 42, 44, 47, 56, 61, 72, 76, 84 and 93.
Done are:
4, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 23, 24, 25, 27, 28, 29, 31, 32, 33, 34, 35, 36, 41, 43, 45, 46, 52, 54, 55, 60, 62, 63, 64, 65, 66, 67, 73, 74, 75, 79, 86, 96
That's not bad going!
James
Edited by deleted (Mon 24-Oct-11 19:30:20)