Still reckon the 23rd . Of course it dosnt really make much difference as it still won't be ready for a few months yet
They can't do this on the last day Dec 23rd because it say description here:
*********** ************ Telford, Telford And Wrekin
Works Start: 10 Dec
End: 23 Dec
Low impact, delays unlikely
Location : (PCP8), REAR OF ****************,TELFORD,SHROPSHIRE,TF7***
Description :
Install 11m of 1 way poly duct in Footway,
Install 3m of 1 way poly duct in Verge,
Install 18 metres of power duct in the footway,
Excavate for the base of the cabinet and perform excavation for earth rod/s,
pour the concrete, 3 days cure time,
set erection bolts for cabinet on template excavation for track
and lay BT duct. Erect the cabinet.
Excavation of the power hole (may have to dig back to prove power)
and lay power ducting complete the power connection Backfill and reinstate. site clear
Current status: Advanced planning
They need to pour the concrete for 3 days to cure time!