|
|
Hi,
I was wondering if anyone was able to shed any light on details regarding the rollout of FTTC in the Llanrwst exchange area, particularly Cabinet 1?
I have tried Superfast Cymru and Openreach but neither will give me any useful information apart from quoting 'exchange to be done end of June'.
Can provide postcode in Private Mesage if necessary.
Thanks very much!
Edited by bloodkil933 (Tue 21-Apr-15 19:06:21)
|
|
|
Exchange Name: Llanrwst
Exchange Code: WNLST
Country: Wales
Cabinet: 1
Fibre Phase: BDUK Wales 14a
Fibre Information: FTTC Planned (exchange planned 31st March 2015)
Result Count: Test Skipped
*** Speed Checks Skipped ***
Please note that these speeds are using BT's DSL Checker and uses the lowest and highest values for that postcode and cabinet.
� Had at least 1 issue retrieving information from the BT DSL Checker. Currently it seems that your exchange has yet to be upgraded even though it says end of March 2015, also seems that your down for FTTC, no date set for this as far as I can see.
I can see some schedules for BT to do with laying fibre:
Location: Access req'd TREFRIW TO COED GWYDYR LL27 0JS...
Description: Access req'd into UG network to install new fibre cable...
Location: Access req'd PONT DOLGARROG B5106 GWYDYR ROAD TO WELLS SPA LL32 8JG...
Description: Access req'd into UG network to install new fibre cable...
Location: Access req'd PONT DOLGARROG B5106 GWYDYR ROAD TO TAL Y BONT LL32 8JG...
Description: Access required into UG network...
Location: access req'd B5106 Conway Rd to Tal Y Bont LL32 8JU...
Description: Access req'd into UG network To install new fibre cable...
Location: B5106 CONWAY ROAD TO TAL Y BONT LL32 v8QE...
Description: Access req'd into UG network to install new Fibre network... Not too sure if that's close to you.
Paul
|
|
|
|
According to my sources, Your cab is planned for FTTC. It is on Phase 14a BDUK Wales. I cant see any works on roadworks.org for installation of any Cabinets. I would believe that it shall be completed by March 2016
|
|
Register (or login) on our website and you will not see this ad.
|
|
|
|
Hi Paul,
Thanks for the reply.
Yes, that cabling is going from Dolgarrog to Trefriw (where Cab 1 is located) according to that.
Recently a lot of a work has gone on along where the ducting is because of flood protection, could they be rerouting the to-be fiber cabinet to a different exchange because of access, or probably just fiber for Llanrwst exchange just happens to come this way?
Thanks.
|
|
|
Fibre backhaul from cabinets often goes to the larger exchange in the area
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
|
Ok, Llanrwst is currently the only 21CN exchange in the area, doesn't this mean the exchange is already fiber enabed or am I getting confused?
|
|
|
|
Llanrwst is the handover point / head end for several exchanges including Dolgarrog, so all the fibre cabinets in Dolgarrog and Llanwrst and any FTTP will goto Llanwrst where the Communication Providers (eg BT wholesale, Sky, talk talk) can then connect to network and offer FTTx services
|
|
|
According to my sources, Your cab is planned for FTTC. It is on Phase 14a BDUK Wales. I cant see any works on roadworks.org for installation of any Cabinets. I would believe that it shall be completed by March 2016
Is there anywhere that shows when the Phases are due to go ahead?
My exchange is in Phase 14a, and due to be ready in June 2015, (was March 2015, Dec '14, Sept '14, etc).
My line which is EO, is supposedly going to a new cab P3, and the link below shows that the exchange has been ready since March last year, which is certainly isn't
https://www.telecom-tariffs.co.uk/codelook.htm?xid=9...
|
|
|
The phases are just announcement based, the phase number confers no specific time window for delivery. There are general guides from each phase but you CANNOT rely on that rough estimate.
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
The phases are just announcement based, the phase number confers no specific time window for delivery. There are general guides from each phase but you CANNOT rely on that rough estimate.
ok, the due dates that i posted are the ones that Superfast Cymru have said that it'll be ready by, still no sign of any work in the area. Every other exchange nearby has had some work done except Talybont and still no plans on roadworks.org.
|
|
|
Ok, Llanrwst is currently the only 21CN exchange in the area, doesn't this mean the exchange is already fiber enabed or am I getting confused?
It means that the exchange is connected to the 21CN IP-based backbone instead of the 20CN ATM-based network.
--
Brian
Zen Fibre 2
|
|
|
Would you be able to comment on plans for Llanrwst Cabinet 7 please.
--
Brian
Zen Fibre 2
|
|
|
|
Ah don't worry, my cab is due to be enabled by September, no cabs have been built yet.
|
|
|
|
FTTC Is planned but there are some technical difficulties to be solved
|
|
|
I've just checked roadworks.org again and now it shows.
A487 A487t Talybont Village, Talybont, Ceredigion
IN FOOTWAY/VERGE OPPOSITE TALYBONT TEL EXCHANGE ON A487T TALYBONT VILLAGE, TALYBONT, CEREDIGION, SY24 5HF, A487T TALYBONT
Build 1 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Demolish 1 existing jointbox(s) or cabinet base(s),Erect/Renew 1 PCP cabinet and base (600mm x 300mm x 1000mm),Install 10m of 3 poly ducts in Carriageway,Install 2m of 3 poly ducts in Verge,Install 4m of 4 poly ducts in Verge
Some sign at last
|
|
|
I've just checked roadworks.org again and now it shows.
A487 A487t Talybont Village, Talybont, Ceredigion
IN FOOTWAY/VERGE OPPOSITE TALYBONT TEL EXCHANGE ON A487T TALYBONT VILLAGE, TALYBONT, CEREDIGION, SY24 5HF, A487T TALYBONT
Build 1 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Demolish 1 existing jointbox(s) or cabinet base(s),Erect/Renew 1 PCP cabinet and base (600mm x 300mm x 1000mm),Install 10m of 3 poly ducts in Carriageway,Install 2m of 3 poly ducts in Verge,Install 4m of 4 poly ducts in Verge
Some sign at last  That's just the PCP Phone cabinet not a fibre one, but at least its either a new phone cabinet or they are renewing the existing one.
Paul
|
|
|
I've just checked roadworks.org again and now it shows.
A487 A487t Talybont Village, Talybont, Ceredigion
IN FOOTWAY/VERGE OPPOSITE TALYBONT TEL EXCHANGE ON A487T TALYBONT VILLAGE, TALYBONT, CEREDIGION, SY24 5HF, A487T TALYBONT
Build 1 concrete chamber 2315mm x 737mm x 1565mm deep in Footway,Demolish 1 existing jointbox(s) or cabinet base(s),Erect/Renew 1 PCP cabinet and base (600mm x 300mm x 1000mm),Install 10m of 3 poly ducts in Carriageway,Install 2m of 3 poly ducts in Verge,Install 4m of 4 poly ducts in Verge
Some sign at last  That's just the PCP Phone cabinet not a fibre one, but at least its either a new phone cabinet or they are renewing the existing one.
Paul
This was hiding behind the other one.
PCP3 is a new cab, there isn't another one near the exchange, this should be for EO lines.
(PCP3) SIDE OF 94 MAES-Y-DERI, A487T TALYBONT VILLAGE
Description: Install 2m of 2 poly ducts in Footway,Install 7m of 2 poly ducts in Verge,Provide 1 Cabinet and base (NGA cabinets)
|
|
|
Thanks. No idea of timescales then?
--
Brian
Zen Fibre 2
|
|
|
Would you be able to comment on plans for Llanrwst Cabinet 7 please. I have the following:
Exchange Name: Llanrwst
Exchange Code: WNLST
Country: Wales
Cabinet: 7
Fibre Phase: BDUK Wales 14a
Fibre Information: FTTC Planned (exchange planned 31st March 2015)
Fibre Status: (Planned area) You are connected to cabinet number 7 on the Llanrwst exchange which is in scope for the Superfast Cymru rollout, We are currently working on the technical solution for you.
Result Count: 197
*** Results Removed ***
Please note that these speeds are using BT's DSL Checker and uses the lowest and highest values for that postcode and cabinet.
� Had at least 1 issue retrieving information from the BT DSL Checker. Seems that there may be an issue that they are working to resolve.
Paul
|
|
|
Cheers!
--
Brian
Zen Fibre 2
|
|
|
This was hiding behind the other one.
PCP3 is a new cab, there isn't another one near the exchange, this should be for EO lines.
(PCP3) SIDE OF 94 MAES-Y-DERI, A487T TALYBONT VILLAGE
Description: Install 2m of 2 poly ducts in Footway,Install 7m of 2 poly ducts in Verge,Provide 1 Cabinet and base (NGA cabinets) Ah, that sounds like a Fibre one 
So that fibre cabinet will possibly be about 7m from its PCP Cabinet.
Paul
|