I had FTTP on Demand and they had coiled up fibre outside my house (under ground duct), when the checker was updated I was Stage 1.
When Openreach first pulled rope through, they tried to do the neighbouring properties on the same DP as well, but because the existing telephone cable for them came up behind a tile (tiled porch) it would mean breaking the tile out to access the duct, and they didn't want to do this given the neighbours hadn't ordered (yet anyway). Those houses are shown as KCI 2 Assure with a note that the underground duct has not been evaluated, i.e. they don't know if clear or not.
I should think to be underground and stage 1, then you would have blue rope already pulled through, or already have fibre pulled through.
Edited by E300 (Mon 13-Jan-20 16:55:13)