I have done that. No.
I was wondering why many surrounding localities had it, if my area was still in progress or had been excluded. Is there a local installations team/contact?
By "No" do you mean this?
"At the moment, we don't have any plans to upgrade your area to full fibre, but provide your contact details and we'll keep you up to date if things change - we add new locations into our build plan every three months."
Basically the reason is that they can't build everywhere at once. I'm afraid that's about as good as an answer as you'll get.
There is a high level map in the "
where and when" page, but this is only at the level of exchange areas, not individual properties. If your exchange area is in scope, it will appear here - in brown when "in plan" (typically 18 month horizon), then yellow when due to start in 3 months, then purple when building started.