Thanks, James. I haven't looked closely at any of the entries with the above indicators. Do you have any idea about what the others could represent, please?
100% of the postcode is served by PCP 14, which is due to be FTTC enabled in Phase 9b, resulting in an approximate uplift of 7.93 times your current sync rate.
Going on the 3 month cycle for each phase, phase 9 is October to December so anywhere between that period if the work is completed on time, can easily slip till net year.
If its anything like where I live 1000's of new builds over the last 15 years, they ignored all the ex-TPON cabs, leaving 100's of houses in the slow lane, they would have to have gone past them to get to get to other true copper cabs - I havent seen anything anywhere to suggest that these ex-TPON cabs can be done, I dont know what the technical problem is, but it is annoying. Ive tried to find out but only get the usual response from BT/Openreach. Im not holding out much hope anytime soon.
TPON while annoying is rare, and the differences make it more of a custom job, and with the pressure to get numbers connected the low hanging fruit is being done first