Update on Thanet.
Checking roadworks.org tonight shows more works which look like they could be FTTC installations scheduled over the next 2 to 3 weeks. I've updated the map to show these with yellow push pins. There's still quite a few duct replacements and clearances scheduled as well.
This leaves just three scheduled cabinets to be done, possibly four. I'm not sure if NDRAM 38 at the junction of Abbots Hill & Camden Road Ramsgate has been done, it's not by the cabinet, only place I can think it may be is at the bottom of the steps in King Street, but haven't had chance to get down there to look.
The other three which haven't been done yet and don't appear to be scheduled are the one just up from the Viking Ship (NDRAM 21), the one in Cavendish Street (NDRAM 41) and the one on Margate sea front at the end of All Saints Avenue (NDTHA 8) which is currently a building site.
The other strange thing I've noticed is that a lot of cabinets seem scheduled yet again for power connections, the one in Northwood Rd was dug up a week or two ago, and has now been dug up again, so that's three times in total!