Added 4 more green cabs to the map
http://www.tinyurl.com/hereford-fttc
the deployment reaches an interesting milestone:
25 ish cabs left to do, of which around half are probably installed (and not reported) or in progress. this leaves only about 12/13 left to schedule, based on past perfromance this is maybe 2-3 weeks work.
Notwithstanding any works we can't see of course.
Noticed OR in middle of high town again today (presumably) running tests on fibres.