Planning permisionis not an Unknow.If you are ina Conservationarea you no youneed planning permision and council planning departments have SLA's sothe timescale is not unknown
Nonsense. The council may have an SLA to respond (they probably call it a target though, as there isn't really a contract), but they're not forced to respond with a YES. It can take more time than expected - to the extent that BT have given up in some locations.
Beyond full planning permission, the council have other responsibilities - including control of the highways. The council can request changes to cabinet siting based on the impact to roads (eg where the pavement is narrow, or the site is too close to the road, or blocks sight-lines). Again, I've heard of cases where refusal from the highways dept causes significant problems (cos there's nowhere left to put the cabinet). I was just reading about a cabinet that got located in a churchyard because the roads were unsuitable.
Every cabinet has to go through this process, and most sail through because of the right amount of pre-planning & co-ordination. But some don't - and our whole disagreement is based on these few - there are unknowns in here. Not fully unknown, but sufficient to build the system around coping with those unknowns. There are no guarantees.
Providing power is a known. Power companies have anSLA so aagain that is not unknow. Providing power to cabinitss is so straight forward in 99% of cases it is a joke if BT use this as an excuse foer delays.
Nonsense. Again power companies may have an SLA to respond, but that doesn't mean that power work can be automatically assumed to go right. And of course, the companies can resort to a "force majeure" clause in the event of workforce being needed elsewhere. No guarantees.
My cabinet is a prime example. It is sitting next to a lit roadsign, but that power source obviously wasn't good enough. The first roadworks to install power presumably established this. 2 months later, new roadworks went across the street & over to near a lampost. Obviously still not good enough. A month later, further roadworks went along the path (in the other direction to the original ones). Within 2 weeks, cabinet was made available - the last in the area.
Again - most work reasonably, but some don't.
How many? I doubt you are right that 99% are straightforward, which smacks of a guess to me. My exchange has 43 cabinets, with not all being converted, so even a single problem here amounts to at least 2.5% - yet my cabinet wasn't the only one delayed by power. My personal guess would be that the figure is nearer 10-20%.
If there are power delays in99% of cases it is because BT forgate to put inan order in a the required timescales tothe utility companies.
I think you are exaggerating a little to suggest that "there are power delays in 99% of cases."
It is ludicrous to believe that, in a nationwide rollout involving 2,000 exchanges and over 40,000 cabinets, BT regularly "forget" to put in an order for power. Poppycock.
But I bet it happens to a few.
Ican assue you Power companies know where their cables are..
And I can assure you that they don't know the state of them all.
This is the real world. Things go wrong. The plans come unstuck in places. The system is designed to get over it - without throwing money at it - at the expense of delaying some cabinets. Live with it.