Facts for those who like to base their comments on them. ( yes it repeats an earlier post that people seem to have ignored)
I have kept spreadsheets from various dates and the reality is on 27/06/2012 Openreach had 171 exchanges planned for Sep 2012 ( none for June). 153 for Dec 2012.
By 02/08/12 they had enabled 19.
By 03/09/12 a further 29
By 25/09/12 a further 63
Total 111, 98 show on the June 'coming soon' list as Sep 2012 and 11 show as Dec 2012 and 2 were not on the list at all!
So 73 (42%) of the Sep 2012 were not completed to date, but 13 are ahead of the list.
Gives 58% completed as of 25/09/12 but I would count these again next monday to get the accurate count.
Also 7% of Dec are already complete in advance so someone should be happy somewhere!
A couple of comments:
- You may need to go further back to properly comment on the state of the "September" exchanges. As you noted, some December ones moved forwards - so how many of the original September batch moved forward into June (or March)? And conversely, how many from March/June got delayed back into September?
- "Completed" is a bad word to use. Once the exchange is announced RFS, we're only halfway there ("half" being an approximation). BT say they open up the exchange once 10 cabinets are ready, which might only be a small proportion of the total. (The number 10 was recently discussed as myth, but I found the
BT page that describes this)
-Counting exchanges is one thing, while counting cabinets would be better. September's exchange-count could be low because engineers spent more time completing cabinets within the June exchanges. Or it could be a high exchange count, but a low cabinet count.
Someone on here is keeping tabs on all the cabinets in the Margate area. I don't know how they're getting all the information, but it is the kind of detail needed to show actual on-the-ground progress.
But...
Don't let these comments put you off - because the more detail, the better. Counting exchanges is all we can do, and these facts are indeed useful.