General Discussion
  >> Fibre Broadband


Register (or login) on our website and you will not see this ad.


Pages in this thread: 1 | [2] | (show all)   Print Thread
Standard User deleted
(deleted) Sat 06-Oct-12 20:09:24
Print Post

Re: BDUK Intervention Program Framework Agreements


[re: deleted] [link to this post]
 
In reply to a post by Bob_s2:
Claw back is a mandatory EU requirement where public subsidies come into play.This requirement cannot be taken out of the contract.

Are you suggesting that your original post was a waste of everyone's time spent reading & responding?

If they're mandatory, and can't be removed, surely there was no need to confirm their presence?
Standard User deleted
(deleted) Sat 06-Oct-12 20:18:50
Print Post

Re: BDUK Intervention Program Framework Agreements


[re: deleted] [link to this post]
 
Actually, it appears to be optional under certain circumstances.
Standard User RobertoS
(sensei) Sat 06-Oct-12 21:36:58
Print Post

Re: BDUK Intervention Program Framework Agreements


[re: deleted] [link to this post]
 
So that post of his is incorrect then.

He seems unwilling to provide information that would allow verification of the opening post as well, wrt to the EU provisions being relevant to all BDUK funding.

I think tbb should introduce a new poster classification, e.g. timewaster, a per post fee being applicable to such and taken by Direct Debit ten days after an email notification of the amount soon after the end of each month.

Any suggestions for the FPP? (Fee Per Post, but I expect other meanings could be assigned - I haven't tried).

My broadband basic info/help site - www.robertos.me.uk | Domains,website and mail hosting - Tsohost.
Connection - Plusnet Extra Fibre (FTTC). Sync ~ 56.0/13.9Mbps @ 600m. - BQM

"Where talent is a dwarf, self-esteem is a giant." - Jean-Antoine Petit-Senn.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
Allergy information: This post was manufactured in an environment where nuts are present. It may include traces of understatement, litotes and humour.


Register (or login) on our website and you will not see this ad.

Standard User deleted
(deleted) Sat 06-Oct-12 22:22:00
Print Post

Re: BDUK Intervention Program Framework Agreements


[re: RobertoS] [link to this post]
 
In reply to a post by RobertoS:
So that post of his is incorrect then.

In a couple of minor ways, it appears.

On clawback itself:
If the "local body" are using the framework, then the clawback stuff is included. As far as I can make out, it is really associated with recovering subsidies where actual cost is lower than predicted, or if the take-up is higher than projections, or if the network is used for non-broadband stuff (presumably voice or leased-lines?). BDUK recommend that the recovered money is spent on getting broadband deeper in the area - which presumably means it gets spent with the same bidder again!

It doesn't appear (from the framework guidance on clawback) to appear to relate to contract penalties.

The guidance is dated July 2012, so I guess this whole topic is a little late, too.

When isn't it mandatory:
First, the "local body" can be applying for BDUK aid, but not following the framework - in which case BDUK merely recommend that the clawback provisions are included. It isn't clear if the "local body" could be something as large as a county council.

Second, it is seen to be an unnecessary administrative burden on small community projects of under £150k.

All-in-all, I'd say that it sounds fair enough as a clawback, and even useful to the counties. It offers an incentive: If they get take-up higher than projected, they can expand the coverage!

(If you ask me, this aspect is *worth* posting about - and singing & dancing about - but was made invisible by the OP's agenda on only posting news that appears to be bad news to BT, and doing so without links)

He seems unwilling to provide information that would allow verification of the opening post as well, wrt to the EU provisions being relevant to all BDUK funding.

Yes - the whole concept of linking to source information seems to be a standard practice, but alien to the OP. I'm not sure why.

I think tbb should introduce a new poster classification, e.g. timewaster, a per post fee being applicable to such and taken by Direct Debit ten days after an email notification of the amount soon after the end of each month.

Any suggestions for the FPP? (Fee Per Post, but I expect other meanings could be assigned - I haven't tried).

It should be like the electricity DNO's: they'll only start to plan it in when the fee has been paid.

More seriously though, other forums have different solutions to applying "karma", "rep", or "likes" to various posts - and a mechanism to hide the posts that don't get a sufficient level of support. Extending this concept so that threads can't be started until you have a good level of "rep" would be useful.