lfor the avoidance of doubt and to deal with some of the misconceptions and franly pettty sarcastic remarks ti will try and give you a view on this
There are a number of triggers to determine aorund Exchanges / cabs- trigger 1 Exchange is either enabled or Not (Y/N) -- if N (then Nothing) if Y then each cab is determined whether it will enabled (god value fo rmoney/size./ Cost Erc (Y/N -- if yes is then built if no it is then left
once those cab that are being built are done the exchange is advises as being enabled -- this is consistent right across the uk
there are a number of reason why cabs get delayed / removed -- some of these include -- no access to site / ennorous conservaiton / objections/other planning permission in place - etc / Highways -- oither utilities / cost of power --
FYI an objection can either dely the cab indedifately (each deal normally around 6 months to 2 years (depending on the workstack which is scheduled months in advance) or remove it all together in some cases. You have to remember this is about premises and coverage and milestones -- so if one cab get removed in exchange X you find another onle somewhere else in Exchange Y (around the same cost and premises count) to replace it