(newbie) Thu 30-Apr-15 23:51:07
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
In reply to a post by Salem874:
On a positive note, my postcode is showing as my cabinet should be live by 30 June on Connecting Cambridgeshire's website...
In reply to a post by Salem874:
Clicking on my property on Connecting Cambridgeshire's Coverage Map page, In addition to being told that cabinets are due to go live by 30/06/2015, It is now also listing TWO coming soon cabinets. Stretham P2, and Stretham P4.

The question now is, is the coverage map accurate to postcode level rather than property (which I guess would be the case). Also, which cabinet am i likely to be connected to, 2 or 4? Given that Cabinet 2 is about half the distance from my property than 4, I'm guessing 2 would make more sense. And if so, i guess it'd be likely to be on FTTP. Surely they wont (I wouldn't have thought they could, given the distance bwteen the two) put the phone on one cabinet and use the other for internet? Or is it gonna be a case of luck which cabinet the Openreach engineer decides to connect us to, hence why both are being listed?


In reply to a post by FredTheB:
Cab 2 is planned for FTTP in BDUK Phase 11a for Cambridgeshire.
Cabs 3 & 4 are both planned for FTTC later on this year


So few weeks ago, Connecting Cambridgeshire listed both P2 and P4 as cabinets when clicking on my property.

Checking this again today, it's not only listing P2, the existing Cabinet which is nearer to my EO property than P3 & P4 which is being installed nearer the exchange. This makes sense to me given that i'm nearer P2 than i am any of the other possible connection points, especially if the reason for P2 being FTTP is due to the distance from the exchange. The only strange thing is the go-live date of P2, which is now listed as 30 March (it was previously 30/06/2015 as noted above). I guess it's time to ask Connecting Cambridgedshire for an update.

Has anyone else heard any more news? Would P2's live date depend on things like Power which appears to be worked on at the new P3 & P4 sites as of tomorrow, or do we think it's ready as-is.

BT Total Broadband (8Mb) - waiting (im)patiently for FTTx
Standard User deleted
(deleted) Sun 03-May-15 11:57:34
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
Not heard a thing, but then I haven't been in touch with Connecting Cambs since i'm assuming 30/06/15 will be when cab 2 goes live with FTTP, around the same time either cab 3 or 4 (or both) go live. Am actually wondering if all the activity there wis for an aggregation node (or maybe a handover node) for all 3 cabinets.

All speculation, though.
Standard User Salem874
(newbie) Mon 25-May-15 18:45:08
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
In reply to a post by Salem874:
In reply to a post by Salem874:
On a positive note, my postcode is showing as my cabinet should be live by 30 June on Connecting Cambridgeshire's website...
In reply to a post by Salem874:
Clicking on my property on Connecting Cambridgeshire's Coverage Map page, In addition to being told that cabinets are due to go live by 30/06/2015, It is now also listing TWO coming soon cabinets. Stretham P2, and Stretham P4.

The question now is, is the coverage map accurate to postcode level rather than property (which I guess would be the case). Also, which cabinet am i likely to be connected to, 2 or 4? Given that Cabinet 2 is about half the distance from my property than 4, I'm guessing 2 would make more sense. And if so, i guess it'd be likely to be on FTTP. Surely they wont (I wouldn't have thought they could, given the distance bwteen the two) put the phone on one cabinet and use the other for internet? Or is it gonna be a case of luck which cabinet the Openreach engineer decides to connect us to, hence why both are being listed?


In reply to a post by FredTheB:
Cab 2 is planned for FTTP in BDUK Phase 11a for Cambridgeshire.
Cabs 3 & 4 are both planned for FTTC later on this year


So few weeks ago, Connecting Cambridgeshire listed both P2 and P4 as cabinets when clicking on my property.

Checking this again today, it's not only listing P2, the existing Cabinet which is nearer to my EO property than P3 & P4 which is being installed nearer the exchange. This makes sense to me given that i'm nearer P2 than i am any of the other possible connection points, especially if the reason for P2 being FTTP is due to the distance from the exchange. The only strange thing is the go-live date of P2, which is now listed as 30 March (it was previously 30/06/2015 as noted above). I guess it's time to ask Connecting Cambridgedshire for an update.

Has anyone else heard any more news? Would P2's live date depend on things like Power which appears to be worked on at the new P3 & P4 sites as of tomorrow, or do we think it's ready as-is.


So, I did get hold of someone at Connecting Cambs a few weeks ago, but have unfortunately been really busy and this have been unable to get a moment to post an update...

On 1 May, I DM'd the connecting Cambs team asking for an update, especially as my (EO) property now listed Cab 2 (only) with a go live date of 31/03/2015 (note in MAY) when it had previously been 30/06/2015.

In summary, the response I got was...

1) "Both" EO Cabinates are due to go live in June
2) Two FTTP Structures due to be erected on Cambridge Road (A10) to continue through to September
3) My postcode is flagged as FTTP
4) FTTP taking longer as requires extensive work, including traffic management and work that needs to be carried out at night.
5) Difficult to give timelines for EO lines, due to these complexities, for this reason a time frame of between Mar - September is being "quoted".

So...given the above, I now know my property should indeed be FTTP (given my postcode is flagged as such). Despite the statement the FTTP roll-out could be completed as late as September, clicking on my property still quotes 30/09/2015 as the "go live" date on their coverage map (which appears to again have been reverted to the previous version which listed both Cab 2 & Cab 4 when clicking on my property). If the dates listed are still correct, i might be "easier" FTTP roll-out (if there's such a thing), either that or they'll delay it again. We already kno that Cab 2 is FTTP, where as Cab 4 is FTTC, so i guess i'm on Cab 2?

I've just had another look at RoadWorks.org.uk, work is scheduled Thursday & Saturday (28-30 May) on the intersection at Wilburton Road/A1123 & Breach Lane. The description of this work reads as follows:

BDUK 3 NIGHTS OF MULTIPHASE LIGHTS ON JUNCTIONS AND 2 WAY LIGHTS ON OPEN STRETCHES REQUIRED FOR SAFE ACCESS TO SURFACE BOXES....

One ting to note is, that this work looks to be planned for overnight. Additionally, it is positioned in an area which (according to Connecting Cambridgeshire's coverage map) already has Superfast Broadband available (marked in green). Clicking on the approximate spot, lists Haddenham Cab 3 (Live) and...the FTTP Stretham Cab 2 (Coming Soon). With this info, I am (slightly more hopeful that we might indeed be able to order by the end of June.

One question that's on my mind though, why MUST work be carried out at night? I take it this is due to the locality/local roads/environment and not really a general case for FTTP infrastructure right?

BT Total Broadband (8Mb) - waiting (im)patiently for FTTx


Register (or login) on our website and you will not see this ad.

Standard User deleted
(deleted) Mon 25-May-15 20:41:06
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
Yeah, in that particular instance the map is wrong. Breach Lane would definitely be Stretham cabinet 2 rather than Haddenham exchange cabinet 3, otherwise that would be some fairly strange network arrangement lol

I haven't contact Connecting Cambridgeshire myself, i've had some personal issues to deal with so haven't had the time.

The last time i checked our new go live date was 30/06/2015. Again, breath will not be held wink
Standard User Salem874
(newbie) Thu 28-May-15 21:14:59
Print Post

Re: Broadband roll-out held up in Stretham


[re: deleted] [link to this post]
 
Things are looking up.

So, after a longer day at work, came home, and to see three men Openreach in high vis jackets walking down the road, carrying those temporary barriers, at about 20:00. All three gathered and stopped outside the manhole cover (is that what you call them) just outside...

So they are working from this evening. Had a not been so exhausted, I'd normally go and try and find out specifics. Maybe tomorrow..

BT Total Broadband (8Mb) - waiting (im)patiently for FTTx
Standard User deleted
(deleted) Fri 12-Jun-15 18:25:13
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
A wrong click on the BTw checker shows at least one of the new PCPs is up and running with lines connected to it. PCP4 I think.
Standard User Salem874
(newbie) Sun 14-Jun-15 13:47:57
Print Post

Re: Broadband roll-out held up in Stretham


[re: deleted] [link to this post]
 
In reply to a post by EddyTheDog:
A wrong click on the BTw checker shows at least one of the new PCPs is up and running with lines connected to it. PCP4 I think.


thats Interesting. Cant you remember which wrong click(s) you made?

BT Total Broadband (8Mb) - waiting (im)patiently for FTTx

Edited by Salem874 (Sun 14-Jun-15 13:52:34)

Standard User deleted
(deleted) Sun 14-Jun-15 13:51:57
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
I think it was the phone number for the pub lol. I was after a different one in the list, got that instead.
Standard User deleted
(deleted) Sun 14-Jun-15 13:56:40
Print Post

Re: Broadband roll-out held up in Stretham


[re: Salem874] [link to this post]
 
I just checked again. It's PCP4, which is now live and accepting orders, apparently.
Standard User deleted
(deleted) Sun 14-Jun-15 14:23:18
Print Post

Re: Broadband roll-out held up in Stretham


[re: deleted] [link to this post]
 
PCP3 is in place as well it seems, but not taking orders yet (took me a while to find any part of Stretham it serves!). Is it obvious i've got a bit of time to kill? lol