Both BT and super fast have replied to me and say it'd being replaced but won't be ready until end of October which is the same day my A&A contract is up
So perfect timing although not sure why it would take so long
Planning Permission for the cabinet, the laying of fibre (if cabinet is placed in a different location) and also power.
Also the different teams maybe busy and their next free slot could be 3 weeks from now, the fibre from the corner pit/chamber to the cabinet may even need to be replaced due to the fibre could of been fractured.
Also the scheduling of the different teams might also add delays and "could" be like the following:
- Get Electric Company to cut power.
- Get BT Engineer to disconnect copper lines and fibre.
- Get Installers to remove cabinet.
- (skip if in same location) Get roadworks to fill in old pit and dig new pit.
- Get installers to install new cabinet in its old or new location.
- Get BT Engineer to connect up all fibre and copper bridge.
- Get Electrical Company to connect power.
- Do loads of tests.
- Go Live.
The time is getting all the different teams allocated to the job, which is why you see some cabinets just sitting there with nothing done to it for ages.
We have the same with our brand new PCP Cabinet which is located a couple of feet away from our old PCP Cabinet, TBH I am not even sure if BT have done anything with it yet.
So that's why it can take a while to go from being installed to going live.
Paul