Well good luck to you... I hope it is for Fibre Jointing and that the completion is soon..
Well 4th try was a charm, I have seen 3 other lots of work for this just appear on roadworks to either just disappear on the day the work was suppose to start or 5 mins after being submitted, so I was rather glad when I heard power saws roaring about 8:30 this morning.
Decided on taking a walk to see, where I saw 2 workers from Conways, one guy in the pit digging and the other sweeping up
Took a couple of pictures shown below of the dug hole and all the cables, fibre tubing, phone and fibre enclosures, oh and loads of blue string that looks rather new.
The blue string may of been put in place ready for the fibre tubing by BT the other day.
Anyway here is the two pictures:
Whole Pit and Hardware,
Close-up of Hardware
I am not too sure what the thin black cable with the yellow plastic wrapped round it is for, but it goes into the fibre enclosure along with the fibre tubing.
Not too sure what the thing enclosure is for, maybe for a few extra phone lines maybe.
Also they was suppose to be doing the following:
- Build 1 concrete chamber 915mm x 445mm x 965mm deep in Footway
- Build 1 precast jointing chamber (725mm x 225mm) 600mm dep
Spoke to the Conway workers and asked about whats going into the pit, and was told red bricks, so I gather that was part 1 and maybe somebody else will be doing part 2 of the work, the work is down for the 15th to 17th.
Paul
Edited by PaulKirby (Mon 15-Jun-15 11:03:25)