September Update
Phase 1 to compelte by the end of September 2015- project is currently at 100 live cabinets with another 24 by the end of the project, 19,768 total homes passed at current.
Phase 2- Details are from the September Digital Champions Update
West Berks- Gigaclear
Gigaclear and the Superfast Berkshire team are analysing data to confirm exactly which West Berkshire premise are eligible for phase 2 state aid funding and therefore within the scope of phase 2. Once we have an agreed list of properties, Gigaclear will provide us with a high level roll out schedule before the end of September 2015, detailing which communities will be completed in what timescale. We will publish this schedule and the list of properties on the SFB project website. 11,700 properties to be covered.
RBWM - 11 cabinets have been identified that will be upgraded to FTTC in areas around Windsor, Wraysbury, Burchett�s Green and Horton.Work will start in Autumn 2015 and is expected to be completed around mid 2016, providing an upgrade to more than 1,750 premises.
Reading and Wokingham - Assuming contracts can be awarded, there will be solutions providing a combination of FTTC, fixed wireless and a small amount of FTTP. If BDUK�s EU State Aid authorisation can be completed later this year, then implementation is still expected to be completed before the end of 2017. The Call Flow proposals provide coverage for 1,550 premises in Reading and 3,250 premises in Wokingham if contracts are awarded.
Alot more coverage to come but just waiting on deployment plans and contacts.
Edited by deleted (Fri 11-Sep-15 17:04:46)