Can anyone provide any details on LCBRI FTTP status specifically Lower Wheelton. The information from BT is non existent. The project completion date was supposed to be August 2014. A year on and we're still no closer is seems. Any information gratefully received
|
|
|
Exchange is a mixture of C and P, cabinet 1 is the FTTP area and appears live, so the question is where are you.
Address XX, MALT HOUSE COTTAGES, VICTORIA ST, WHEELTON, CHORLEY, PR6 8HH on Exchange BRINSCALL is served by Cabinet 1
WBC FTTP Up to 330 Up to 30 -- Available
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
|
PM'd you details.
|
|
Register (or login) on our website and you will not see this ad.
|
|
|
End result is it looks like the job has been half down and nothing on roadworks.org
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
Can anyone provide any details on LCBRI FTTP status specifically Lower Wheelton. The information from BT is non existent. The project completion date was supposed to be August 2014. A year on and we're still no closer is seems. Any information gratefully received  Join the club.
Paul
|
|
|
|
I assume that some of the premises were reachable as FTTP and some were not
I assume those that were reachable have been already done
|
|
|
Looks likely that its a delay as fibre gets run down a road linking the two large clusters on that cabinet.
FTTP roll-out tends to suffer as in terms of hitting milestones, blowing the fibre for a cabinet gives a quicker result in terms of premises passed.
Will be chasing up with Openreach to find out what the situation is.
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
|
Andrew did you ever gate anything back for my FTTP rollout that has been delayed.
I know I sent you an email on the 18 August and you sent me an email reply on the 25 August saying to sit back and see what will happens, its been over a month since then but sadly still no new work on roadworks, or the database going live, nothing.
So either there has not been any need to dig up any roads etc so far or there hasn't been any new work done.
Once again, thanks for the help.
Paul
|
|
|
Can't remember, do sometimes miss the odd email particularly those that arrive when out and about, so email me again from same address and will double check on Monday morning
|
|
The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
|
|
|
Can't remember, do sometimes miss the odd email particularly those that arrive when out and about, so email me again from same address and will double check on Monday morning Resent, and thanks.
Paul
|