Just to be clear, when the orders for Fibre were placed they were accepted by ISP, a week later Openreach have come back saying 'No spare ports at the DSLAM'. I didn't have any real chance of ordering it earlier, as I hadn't taken ownership of the location. I am still surprised that an order can be accepted by the ISP and Openreach and then a week later rejected. It would be really helpful if Openreach could tell the ISP roughly how long a resolution would be.....
Yes, I was being flippant - hence the smiley
I am also surprised your ISP were able to accept an order and then have it rejected a week later - most ISPs will have an automated ordering system which I imagine would place the order with Openreach within seconds if done online - and at that point Openreach should reserve a port at the Cabinet for you/update capacity for future orders.. so is it possible your ISP delayed placing your order?
Generally speaking, if you place an order against a line (even for something like call waiting),the wholesale checker updates within hours to say there is an open order against that telephone number.
If there was no capacity and the ISP are not using the new waiting system, I would have expected them to be unable to place an order.
As I say, Openreach tend to update the wholesale checker with the date they plan to fit more line cards once scheduled - someone who works for Openreach may be able to comment on average timescales but its a simple job - it usually just depends on them allocating the task + spare linecards to an engineer/contractor to do
If a newly commissioned Cabinet its very unlikely to be another issue unless they have found a fault with the equipment already installed and that should have been picked up during pre-commissioning testing..