Standard User thebigdolphin1
(member) Wed 21-Sep-16 17:20:27
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
Well, there goes all my hopes.

Have you any idea why the upgrade to the cabinet may have been delayed from 2012? I've always assumed blocked ducts were the issue, but if they haven't even installed them then it couldn't have been the cause. Takeup certainly wont be the issue as there's over 500 connected premises with less than 8Mbps.
Standard User deleted
(deleted) Wed 21-Sep-16 17:39:42
Print Post

Re: Cabinet information query


[re: thebigdolphin1] [link to this post]
 
New duct is often required to bypass blocked or congested ducts.
Many cabinets have been put on hold for lengthy periods if actual civils are significant, presumably until BDUK coverage is at/near completion and they need to get delayed cabinets running.
Standard User thebigdolphin1
(member) Mon 26-Sep-16 18:54:02
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
Well, you were right. The expected happened.


Register (or login) on our website and you will not see this ad.

Standard User deleted
(deleted) Tue 27-Sep-16 22:41:27
Print Post

Re: Cabinet information query


[re: thebigdolphin1] [link to this post]
 
It's back on...
Standard User thebigdolphin1
(member) Tue 27-Sep-16 22:43:04
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
Yeah, they appear to have re-listed it earlier today. Still not a good sign that they're uncertain though.

Edited by thebigdolphin1 (Tue 27-Sep-16 22:43:17)

Standard User thebigdolphin1
(member) Wed 05-Oct-16 10:56:18
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
They've either completed it or delayed it for another year. I wonder which...
Standard User thebigdolphin1
(member) Thu 20-Oct-16 13:44:40
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
Hey! I've received a more detailed response from Openreach regarding out cabinet:
The project is still ongoing and we have estimated date of completion as End of November 2016, which is subject to change depending on the progress of the project.
The work is pending with Line Plant Approval/ Civils Team, and we are expecting the work to be completed by the End of November 2016.
Standard User PaulKirby
(fountain of knowledge) Thu 20-Oct-16 15:39:27
Print Post

Re: Cabinet information query


[re: thebigdolphin1] [link to this post]
 
In reply to a post by thebigdolphin1:
Hey! I've received a more detailed response from Openreach regarding out cabinet:
The project is still ongoing and we have estimated date of completion as End of November 2016, which is subject to change depending on the progress of the project.
The work is pending with Line Plant Approval/ Civils Team, and we are expecting the work to be completed by the End of November 2016.

Nice, lets hope its done by then smile

Paul

BTBroadband - Infinity 4 - 310Mbps (down), 31Mbps (up)
Standard User deleted
(deleted) Thu 20-Oct-16 17:04:25
Print Post

Re: Cabinet information query


[re: thebigdolphin1] [link to this post]
 
Thanks for the update!
Standard User deleted
(deleted) Thu 20-Oct-16 19:33:06
Print Post

Re: Cabinet information query


[re: deleted] [link to this post]
 
I'm curious, how accurate is 'code look' when it comes to due dates for cabinets to go live?

Mine says live by October 2016 lol. Stuck on March 31st 2017 on bt wholesale though