Thank you for digging up that post.
Residents chose to go with BT at our AGM in November 2014 and after further negotiation with BT I signed the contract on behalf of the residents in late March 2015. Our AIO cab was stood in December 2015 after Lambeth had objected to its original location. Lambeth then caused a further delay by serving a section 58 notice and the actual network rearrangement and installation of the fibre didn't occur until Jul-Aug 2016. We finally went live in September 2016. Final cost was a little under £250 per property inc. VAT.