my fibre on demand story with Cerberus
exchange = Whitchurch race to infinity winers
21/06/2019 - Paid for survey
27/08/2019 - Confirmed FTTP on Demand Build cost
Labour £5,245.36
Contract Labour £0.00
Civils £750.00
Stores £3,690.30
BT Connection Charge £495.00
Deduction £-1,050.00
Field Survey charge paid £-250.00
Total £8,881.00
7 Premises passed. Deductions of £50 per premises and £700.00 per FTTPoD order
Confirmed Build Charge ex VAT £8,881.00
Confirmed Build Charge inc VAT £10,657.20
Voucher £2,500.00
Amount Due £8,157.20
(of which VAT) £1,776.20
08/09/2019 Paid Above
21/11/2019 Current Status: Provisional traffic notice submitted for road closure with a start date of 17/02/20. Onsite between 21:00 to 06:00 for 3 nights
16/12/2019 – over head fibre added from pole opposite house on the far side of road to pole 20 yards down from house on the near side of the road with coils left on both poles
17/02/2020 openreach on site for 3 nights (coils on poles remain untouched)
21/02/2020 I asked if had been any problems
26/02/2020 Current Status: Cabling completed 26/02/20. Jointing now required
28/20/2020 more overhead fibre added now from pole 30 yards up from house on near side of the road to pole 20 yards down from house on the near side of the road and also an 8 port fibre manifold added
09/03/2020 update - Current Status: Jointers have found a blockage between a pole and a cable chamber box very close to your premises
30/03/2020 update – blockage cleared
03/04/2020 update - I have received confirmation that the jointing work has now been completed
13/05/2020 Openreach engineer on site for final audit – he was very confused that the fibre installed on the 16/12/2019 was still in coils of both poles but the fibre is active
15/05/2020 2 Openreach engineers on site removing unused fibre
18/05/2020 BT checker shows FTTP as available
26/05/2020 call from Openreach with install date of 08/06/2020
Edited by isar (Mon 01-Jun-20 14:24:24)