And at the current rate, they won't get to 25m properties until March 2029. They are going to have to crank things up substantially to meet the Dec 2026 target.
It’s fast, but not fast enough! They were making headway at c.70K per week
at one point, but if you were to draw a straight line you get:
Weeks to 31 Dec ‘26 = 256
Properties to pass = 25M - 6.5M = 18.5M
Required (average) run rate = 18.5M / 256 = 72,266
So the current run rate is 22,265 per week short. In other words they have to accelerate (on average) by 44% over the current average run rate.
Either they have to ramp this up or as you say at the present run rate, they won’t pass the 25M mark until the end of first quarter of 2029.