Hello folks - I would like to ask for opinions on how long it tends to be after a rural Openreach FTTP area is fibred and when it is opened for ordering by the Sales teams?
The situation is that in South Ayrshire we have seen the fibres go up on the existing poles, local duct work is complete to our small housing cluster, disparate segments of fibre off the trunk to our roads are joined and finally a "lighting up" team have concluded their work successfully.
That was two months ago with no further local activity. The Openreach website does not show us as available yet although I am on the "tell me when I can order" mailing list.
Do they tend to complete a wide area before letting everyone in or is it unlocked section by section as it is completed?
Cheers,
Daniel.