We are also in the middle of a rollout and the planning appears good for 100% take-up.
I have just had a look at the blocks of flats, each now has a CBT attached to the wall about 3m up with enough ports to cater for each flat. Most of the Pole fed houses have enough CBT capacity to cater for 100% of the existing drops.
I am keeping an eye on the exception which is an overloaded pole with 48 plus drops to houses and flats connected to it. (Some will be obsolete). Last week the old ceramic isolators were removed leaving a birds nest of wires. The flats have already been catered for as above allowing fr the future removal of three of the multi pair cables.
Talking to the group of OR workers and contactors gathered around the base they are going to try to place 3 CBTs if they can find room when up there. and are hoping that the number of workers is below 36! (The area has Virgin already) The OR engineers said the limit is meant to be 30 drops but there are so many they couldn't count from ground level! always losing count at somewhere over 40! . They were also wanting to connect 2 fibre cables in addition for the two CBTs they had just installed on a subsidiary pole and were worried about adding extra strain on the pole.
I am waiting with interest to see what the final solution they come up with is.
Have to wait for another day, they got the fibre cables up but there is not enough room for the CBTs so they are going back to the planners..