Drawn a bit of a blank here so far!
In summary what I’d like is some expert opinion on please is whether my 1962 built cul de sac with a footway box for each pair of houses would be expected to have been built with duct between the boxes or ‘it depends’.
As already stated I know for a fact there’s an incoming 2” duct into the box serving my own house (I’m end of the road so no outgoing duct).
Given your cynicism over the information Openreach have provided I'd suggest having a look yourself. Cable and duct look quite different in the boxes and be easy to tell which is which.
The nature of the chambers and that there's one every other home strongly indicates no duct as standard. Even if there's duct and it's all usable getting to each home will require digging and new chambers will be required to hold the CBTs.
From their point of view nothing to rod and rope and presumably inspecting chambers in the main road would've told them what they needed to know about the feed to your street alongside their records. They haven't built ducted network with that type of chamber anywhere they've only installed duct as a repair when a directly buried cable failed. I can't speak for the actual experts but the areas where cable was directly buried or used tiny ducts to homes that did have duct between boxes used more regular chambers not JB22s ever other property.
Not impossible that the building of it went rogue of course just vanishingly unlikely and they presumably are confident enough that a survey of every chamber on the off-chance not required.
On the point with the lack of pavement scars it's perfectly possible that the cable to your box failed during install and was repaired before the final fix was done to the pavement. Both cable and duct fail most frequently during reinstatement above them. Like most things a spike of unreliability right at the start then stable for ages. If you were to follow streetworks building a new ducted network you'd see those then some more to unblock and repair anything that took on silt or was crushed.
If they did other streets that you know are built the same way yours is and it took extensive civils that's your answer there. They haven't built to you because they've gone over budget for the project. Until they find some underspend, get more budget from the wider company or are given government subsidy they won't continue. Just the costs of building the new chambers put you outside of the regular budget window let alone digging in between the new chambers and new build to get to each property.
Depending where in the country you are VMO2 should have you covered with full fibre in the not too distant. If you've a new cabinet next to the older ones they probably have fibre ready to go.