They are pretty very quick job from start to finish for FTTP. Very impressive.
Stage 1: 9 x Poles go up Dec 15th & 16th
Stage 2: 9 x Poles overhead fibre cable Dec 16th & 17th
Stage 3: Pull fibre cable from 1 x pole to underground pathway chamber fibre aggregation nodes & 3 x poles fibre splitter using Optical Fibre Cleaver Dec 18th & 19th
Stage 4: Final check & commissioning Dec 19th
Stage 5: Checker updated on BTW Checker (Saturday December 20th after 5pm) to say FTTP now ready to order (Openreach Checker will follow soon to updated)
Stage 6: Checker updated on Openreach Checker (Monday December 22nd after 12am) to say FTTP Available to order now with FTTP up to 1600Mbps down and up to 115Mbps up
Took them just 6 days from December 15th to 20th