In reply to a post by Ignitionnet:Regardless of semantics applications needed to go into the borough council before cabinets could be built, none were. This is the same process that governs street works too.
I'm not saying that planning had/hadn't been carried out. The part of RandomJointer's post that I am referring to is:
In reply to a post by RandomJointer:I would have a guess that some delays were down to maybe Openreach considering FTTC cabinets as minor works and maybe some councils considering FTTC cabinets as major noticeable works.
Minor, Standard & Major works notice/permits add additional time on top of the planning phase. Obviously, if planning permission is required, then this should have been sorted out before noticing/permitting.
**Edit**
From what I have recall, the majority of cab works have been Standard works. Then again the cab works haven't reached the areas that will directly affect me yet.