In reply to a post by baby_frogmella:Alternatively, like i did, you may get fibre blown from the DP to your premises which is usually 4 fibre strands in 1 tube - this will terminate at a Customer Splice Point (CSP) outside. From there they splice 1 fibre strand to a lead-in fibre cable which terminates at the ONT. The remaining 3 fibre strands are kept as spares in the CSP all nicely coiled up. TBH i don't think you will need any of the 3 spares as the single live fibre strand supports at least 4 FTTP lines.
Did they push/pull the fibre tube through the duct first then blow the 4 fibre strands down the fibre tube afterwards or did they blow them all through together?
Not 100% sure as I didn't watch them do it but I believe they first put in the black/yellow tubing in the duct and then the fibre was blown in. The Distribution Point (DP) is only 20-30m away with relatively new ducts so it was quite an easy job for Openreach.