Just gone live today with our FTTPod
Timeline �
12/07/18 Requested desktop survey
23/07/18 Full survey requested & paid.
30/08/18 quote received
07/06/19 final commission & test
Our fibre node is exactly 5.5 metres (not a typo) from our building � it�s taken 11 months of pain to get connected, that�s an average of half a metre a month!
Looks like we�ve just managed to swerve any 12 month grant issues.
Was it worth it - oh yes
Phil
We went live on Monday PM. My timeline is eerily similar to yours:
02/07/18 Requested desktop survey
12/07/18 Full survey requested & paid.
24/09/18 Final quote received
10/06/19 final commission & test
Mind you our aggregation node is roughly 1.8km away and requires about 34 pole spans and several underground sections. Clearly time to deliver by OR is not distance dependant.
What was your install cost if I may be so bold to ask? Ours was one of the rare cases on here of the final quote actually being higher than the Desktop EBC (by almost £1500).