Saw some with the light test done, i.e. all fibre in place and lit from exchange but took 4 weeks to appear as ready to order.

Some areas they wait for a wider area to be available before releasing it to order, and others seem to be more piecemeal

The author of the above post is a thinkbroadband staff member. It may not constitute an official statement on behalf of thinkbroadband.
Standard User deleted
(deleted) Wed 04-Mar-20 14:31:10
Print Post

Re: Contractors just fitted this


[re: busterboy] [link to this post]
 
okay thanks. hopefully wont be too long for me either, but then again everytime ive asked openreach online they have said no plans to upgrade my street.
Yet i spoke to the engineer doing it and he said should be ready to order in a few weeks, this was back in January. Since then they've probably hit a blocked duct and had to get that installed.
so fingers crossed it wont be too much longer!
Standard User busterboy
(committed) Wed 04-Mar-20 14:36:15
Print Post

Re: Contractors just fitted this


[re: deleted] [link to this post]
 
In reply to a post by bomber456:
okay thanks. hopefully wont be too long for me either, but then again everytime ive asked openreach online they have said no plans to upgrade my street.
Yet i spoke to the engineer doing it and he said should be ready to order in a few weeks, this was back in January. Since then they've probably hit a blocked duct and had to get that installed.
so fingers crossed it wont be too much longer!


Good luck mate, fingers crossed for you. smile

BTBroadband


Register (or login) on our website and you will not see this ad.

Standard User unknown101
(regular) Wed 04-Mar-20 19:58:18
Print Post

Re: Contractors just fitted this


[re: MrSaffron] [link to this post]
 
A PON can be commissioned within around 48 hours from submission internally to showing availability externally as long as no issues identified during commissioning stages.
Standard User busterboy
(committed) Wed 04-Mar-20 23:22:21
Print Post

Re: Contractors just fitted this


[re: unknown101] [link to this post]
 
In reply to a post by unknown101:
A PON can be commissioned within around 48 hours from submission internally to showing availability externally as long as no issues identified during commissioning stages.


Now that would be nice. grin

BTBroadband
Administrator MrSaffron
(staff) Thu 05-Mar-20 09:03:07
Print Post

Re: Contractors just fitted this


[re: unknown101] [link to this post]
 
Can versus observed