So today was Day 1 of internal install. We now have splice tray / patch panel installed in the cabinet. The external purple blown fibre tube (BFT) has been run in from the node in the street, via a 'sausage' and joined to an internal BFT going to the patch panel. A 12-fibre blown bundle has been installed from the patch panel to the node in the street - initially tried a manual push from the street, but later installed the fibre bundle from the cabinet end out to the street. Much easier.
The NTE is here and ready to be installed.
Hopefully with some remaining splicing at the node in the street, and the installation and connection of the NTE the circuit and service should be good to go tomorrow.
External purple BFT being installed, existing Openreach box below
Working the fibre through from node in the street
Fibre node
I'll add some more photos once the instal is all done